Sunday, 22 August 2010
Brick Cleaning
We started the brick cleaning ready for the walls and roof to be done this week. SHMBO did a lot of the cleaning while I carried on with building foli and window fitting. All the back wall windows are in except the sliding door, the eastern sliding doors are in and the ensuite window. I have 3 slidng doors, 4 large windows and 2 small windows left to install. Getting the roof on will be great and the cladding is on order so it should be ready for the 2 weeks off I have in September.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment