Tuesday, 2 November 2010

Services are roughed in

The plumbers have finished roughing in, all the electrical wiring is in, the ducted vac is finished and the insulation has started going in. Plasterers are a couple of weeks away to give us a chance to ensure we have everything behind the plaster that we need. Once the plasterers start it will take about 4 weeks to finish so I will have work outside to go on with including downpipes and painting. Groundwork can be done anytime other jobs are not required.
The gas meter will end up in a better place than I thought of originally and we have wired and plumbed for a spa. Look forward to that if the money allows.

No comments: