Wednesday 9 February 2011

Architraves and more

We have about 420 metres of architraces and skirting boards. They need to be cut to size, painted twice, screwed into place, puttyed the screw holes and then repainted. We are well underway and will spend most of the week doing it.
Next week will be vinyl for the ensuite and bathroom walls, the natural gas pipes from the road to the meter location and the kitchen will arrive and be fitted along with the laundry cupboards and the bath deck.

Moving along nicely. Plumber due for end of february.