Services are roughed in

The plumbers have finished roughing in, all the electrical wiring is in, the ducted vac is finished and the insulation has started going in. Plasterers are a couple of weeks away to give us a chance to ensure we have everything behind the plaster that we need. Once the plasterers start it will take about 4 weeks to finish so I will have work outside to go on with including downpipes and painting. Groundwork can be done anytime other jobs are not required.
The gas meter will end up in a better place than I thought of originally and we have wired and plumbed for a spa. Look forward to that if the money allows.